An organization uses earned value management to assess project performance. Which of the following sets of values reflects the data that the project manager needs to monitor for earned value management?
- CP, CO, 4CM
- PV, EV, and AC
- EAC, ETC, and BAC
- NPV, IRR, and BCR
The correct answer is 2.
Answer 1 lists PERT data points; answer 3 lists EAC, ETC, and BAC, all of which are forecasting formulas; and answer 4 lists project selecting methods.