PMP Exam Prep Question of the Week

pmpweek05

You are completing a stakeholder register. To what process group does this activity belong?

  1. Closing
  2. Monitoring and Controlling
  3. Initiating
  4. Executing

The correct answer is 3.

The Initiating Process Group is made up of only two processes: Develop Project Charter (in the Project Integration Management Knowledge Area) and Identify Stakeholders (in the Project Communications Management Knowledge Area).