You are completing a stakeholder register. To what process group does this activity belong?
- Closing
- Monitoring and Controlling
- Initiating
- Executing
The correct answer is 3.
The Initiating Process Group is made up of only two processes: Develop Project Charter (in the Project Integration Management Knowledge Area) and Identify Stakeholders (in the Project Communications Management Knowledge Area).