pmpweek07Your project has the following tasks:

Task Duration Predecessor

Name Duration (in weeks)
Predecessor
A 2
B 3 A
C 5 B
D 5 C
E 8 B
F 1 D, E

 

Management has promised the customer that you would complete the project in 14 weeks. What does this mean?

A. You have negative float.
B. You have positive float.
C. You have zero float.
D. You cannot calculate the float.

Reveal Answer