PMP Exam Prep Question of the Week

pmpweek06

An organization uses earned value management to assess project performance. Which of the following sets of values reflects the data that the project manager needs to monitor for earned value management?

  1. CP, CO, 4CM
  2. PV, EV, and AC
  3. EAC, ETC, and BAC
  4. NPV, IRR, and BCR

The correct answer is 2.

Answer 1 lists PERT data points; answer 3 lists EAC, ETC, and BAC, all of which are forecasting formulas; and answer 4 lists project selecting methods.