Your project team is completing the transfer of its final product to the next phase of production. This transfer is the output of what process?

  1. Perform Integrated Change Control
  2. Close Project or Phase
  3. Monitor and Control Project Work
  4. Direct and Manage Project Work

The correct answer is 2.

Although the outputs for the Direct and Manage Project Work and Close Project or Phase processes are very similar, their wording is slightly different. Deliverables are the output of the Direct and Manage Project Work process. Final product, service, or result transition is the output of Close Project or Phase.