A project sponsor has requested information about the cost performance on a project, so you need to determine cost variance. What formula should you use?

  1. AC – EV
  2. EV – AC
  3. EV ÷ AC
  4. EV x AC

The correct answer is 2.

Answers 1 and 4 are not valid EVM formulas, and answer 3 is the formula for determining CPI.