PMP Exam Prep Question of the Week

pmpweek04

You are confirming human resource availability for your project as part of the Acquire Project Team process. Which of the following is not a tool or technique you will use?

  1. Acquisition
  2. Negotiation
  3. Co-location
  4. Pre-assignment

The correct answer is 3.

Co-location is a tool or technique of the Develop Project Team process, not the Acquire Project Team process.