You are conducting the Perform Quality Assurance process to ensure that quality standards have been properly used. To which process group does this process belong?
- Planning
- Monitoring and Controlling
- Closing
- Executing
The correct answer is D.
Answer D is correct. Perform Quality Assurance is the only process in Project Quality Management under the Executing process group.