Which process involves reviewing all change requests and approving and managing changes to the deliverables, organizational process assets, project documents, and the project management plan?
- Monitor and Control Project Work
- Perform Integrated Change Control
- Direct and Manage Project Work
- Close Project or Phase
The correct answer is B.
All items listed in the question are functions of Perform Integrated Change Control.