The team has identified the risk of delayed completion of technical deliverables due to the use of multiple vendors. Missing several project schedule deadlines is an example of a what?
- Risk trigger
- Risk response
- Secondary risk
- Residual risk
The correct answer is 1.
In order to determine if the risk of delayed completion of technical deliverables is increasing or has occurred, the project manager will carefully monitor the schedule performance of the various vendors responsible for those technical deliverables. Missed deadlines are a risk trigger for the risk of delayed completion of technical deliverables.
Related Resources
PMP Exam Prep Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
Please support our Sponsors here :