You want to graphically outline project roles and responsibilities. Which tool should you use?
- Resource Assignment Matrix (RAM)
- Responsibility Assignment Matrix (RAM)
- Responsibility Assignment Grid (RAG)
- Resource Assignment Chart (RAC)
The correct answer is 2.
Answer 1 is incorrect because of the use of the word resource. Answer 3 is incorrect because of the use of the word grid, and answer 4 is incorrect because the tool needed in this scenario is a matrix, not a chart.
Related Resources
PMP Exam Prep Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Exam Prep Question of the Week Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
Please support our Sponsors here :