Which one of the following processes should you use in order to develop strategies to engage stakeholders?

  1. Plan Communications Management
  2. Plan Stakeholder Management
  3. Manage Stakeholder Engagement
  4. Control Stakeholder Engagement

The correct answer is 2.

Plan Stakeholder Management is “the process of developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs and potential impact on project success.”