Various breakdown structures can be used on a project, such as the work breakdown structure. Which of the following is not a structure identified in A Guide to the Project Management Body of Knowledge (PMBOK® Guide)?
- Risk breakdown structure
- Resource breakdown structure
- Organizational breakdown structure
- Timeline breakdown structure
The correct answer is 4.
There is no such thing as a timeline breakdown structure. Answers 1, 2, and 3 are all identified in the PMBOK® Guide.
Related Resources
PMP Exam Prep Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Exam Prep Question of the Week Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
Please support our Sponsors here :