Determine the critical path from the project schedule network diagram for the following project.
Task
|
Duration (in Days)
|
Predecessor
|
---|---|---|
A | 3 | Start |
B | 2 | A |
C | 3 | A |
D | 1 | A |
E | 3 | B |
F | 4 | B |
G | 8 | C |
H | 5 | D |
I | 1 | E, F |
J | 4 | G |
K | 8 | H |
L | 1 | I |
M | 2 | J, K |
N | 1 | L, M |
1. A-B-F-I-L-N
2. A-B-E-I-L-N
3. A-C-G-J-M-N
4. A-D-H-K-M-N
The correct answer is 3.
The A-C-G-J-M-N path has a cumulative duration of 21, which represents the longest path in time through the network. The path duration in answer 1 is only 12, the answer 2 path is 11, and the 4 path is 20.
Related Resources
PMP Exam Prep Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Exam Prep Question of the Week Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
Please support our Sponsors here :