Which of the following processes do not benefit from the outputs of the Develop Schedule process?
- Control schedule
- Estimate costs
- Determine budget
- Form team
The correct answer is 4.
The project schedule becomes an input to controlling the schedule, estimating costs, and determining the budget. Team formation is not a recognized process.
Related Resources
PMP Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Weekly Question Series
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
- PMP Exam Prep Question of the Week
Please support our Sponsors here :