Your team is in the middle of executing a project that is now projected to run three weeks too long. Which of the following adjustments would allow the project to be delivered on time?
- Substitute a lesser experienced programmer for a more experienced one.
- Move resources from a noncritical task to a critical path task.
- Modify the purchase of new equipment to less expensive equipment.
- Allow a tester on the project to temporarily work on another, more critical project.
The correct answer is 2.
Answers 1 and 4 would likely result in adding additional time to the project; 3 would contribute to cost savings, but does not necessarily have an impact on time.