You are estimating the total project cost using three points for cost estimates with a 95 percent confidence level. What is the cost estimate range if the estimated project cost is $120,000 and the standard deviation is $2,500?

A. $115,000 to $120,000
B. $117,500 to $122,500
C. $112,500 to $127,500
D. $115,000 to $125,000