If PV = $10,000, EV = $9,000 and AC = $9,000, what is the current status of your project?
A. On schedule
B. On budget
C. Behind schedule but on budget
D. Insufficient information to evaluate
Related Resources
PMP Exam Prep Mobile App
Project Management White Papers
Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp
PMP Formula of the Week Series
- PMP Formula of the Week: Forecasting a Necessary CPI
- PMP Formula of the Week: Forecasting a Necessary CPI Based on an ETC
- PMP Formula of the Week: Ahead or Behind Schedule
- PMP Formula of the Week: Point of Total Assumption
- PMP Formula of the Week: Rent, Lease or Buy?
- PMP Formula of the Week: Risky Task
- PMP Formula of the Week: Earned Value Management Methodology
- PMP Formula of the Week: Schedule Performance Index of 1
- PMP Formula of the Week: TCPI
- PMP Formula of the Week: Fixed-Price Incentive Fee Contract
- PMP Formula of the Week: S-Curve
- PMP Formula of the Week: Current Project Status
Please support our Sponsors here :