You are using the earned value management methodology. Which of the following is not a status formula you might use?
A. SV
B. BAC
C. CPI
D. CV
Related Resources
PMP Exam Prep Mobile App
Project Management White Papers
Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp
PMP Formula of the Week Series
- PMP Formula of the Week: Forecasting a Necessary CPI
- PMP Formula of the Week: Forecasting a Necessary CPI Based on an ETC
- PMP Formula of the Week: Ahead or Behind Schedule
- PMP Formula of the Week: Point of Total Assumption
- PMP Formula of the Week: Rent, Lease or Buy?
- PMP Formula of the Week: Risky Task
- PMP Formula of the Week: Earned Value Management Methodology
Please support our Sponsors here :