What piece of work performance information provides the most valuable information about a project behind schedule?
A. Cost Variance
B. Status of deliverables
C. Schedule variance
D. Estimate to complete
Related Resources
PMP Exam Prep Mobile App
Project Management White Papers
Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp
PMP Formula of the Week Series
- PMP Formula of the Week: Forecasting a Necessary CPI
- PMP Formula of the Week: Forecasting a Necessary CPI Based on an ETC
- PMP Formula of the Week: Ahead or Behind Schedule
- PMP Formula of the Week: Point of Total Assumption
- PMP Formula of the Week: Rent, Lease or Buy?
- PMP Formula of the Week: Risky Task
- PMP Formula of the Week: Earned Value Management Methodology
- PMP Formula of the Week: Schedule Performance Index of 1
- PMP Formula of the Week: TCPI
- PMP Formula of the Week: Fixed-Price Incentive Fee Contract
- PMP Formula of the Week: S-Curve
- PMP Formula of the Week: Current Project Status
- PMP Formula of the Week: Project Schedule Information
- PMP Formula of the Week: Random Defective Article
Please support our Sponsors here :