You are in the Executing phase of your project. As project manager, you receive weekly status reports on work progress from team members. In reviewing their input, you are particularly interested in two tasks:
- Task 89 has an EST (estimated start time) of 45 and a LST (late start time) of 58.
- Task 101 has an EST of 64 and a LST of 51.
Which of these tasks is riskiest?
A. Task 89 is the riskiest.
B. Task 101 is the riskiest.
C. Risk cannot be determined based on the given information.
D. Both tasks are equally risky.
Related Resources
PMP Exam Prep Mobile App
Project Management White Papers
Related Courses
IT Project Management
Project Management Fundamentals
Project Management, Leadership, and Communication
PMP Exam Prep Boot Camp
PMP Formula of the Week Series
- PMP Formula of the Week: Forecasting a Necessary CPI
- PMP Formula of the Week: Forecasting a Necessary CPI Based on an ETC
- PMP Formula of the Week: Ahead or Behind Schedule
- PMP Formula of the Week: Point of Total Assumption
- PMP Formula of the Week: Rent, Lease or Buy?
- PMP Formula of the Week: Risky Task
Please support our Sponsors here :