The project team is in the control risks process and the team members are preparing the documentation needed. Which of the following is not an output of this process?
A. Organizational process assets updates.
B. Risk register.
C. Change requests.
D. Project management plan updates.
Related Resources
PMP Exam Prep Mobile App
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Exam Prep Question of the Week Series
- PMP Question of the Week: Perform Quality Assurance
- PMP Question of the Week: Quantitative Data
- PMP Question of the Week: Situational Continuum Leadership
- PMP Question of the Week: Stakeholder Register
- PMP Question of the Week: Plan Risk Responses
- PMP Question of the Week: Performance Improvement
- PMP Question of the Week: Budgets
- PMP Question of the Week: EAC
- PMP Question of the Week: Quality Control Techniques
- PMP Question of the Week: Outlining Project Roles
- PMP Question of the Week: Engage Stakeholders
- PMP Question of the Week: Breakdown Structures
- PMP Question of the Week: Quality Management
- PMP Question of the Week: Decision Tree
- PMP Question of the Week: CV
- PMP Question of the Week: Critical Path
- PMP Question of the Week: Project Cost Management
- PMP Question of the Week: Change Request
- PMP Question of the Week: Contract Complete
- PMP Question of the Week: Control Procurements
- PMP Question of the Week: Control Risks
Please support our Sponsors here :