During a facilitated workshop for the Define Scope process for your project, which of the following will not be an input to this process?
A. Preliminary project scope statement
B. Project charter
C. Requirements documentation
D. Organizational process assets
Related Resources
PMP Exam Prep Mobile App
Project Management White Papers
Related Courses
Guided PMP Exam Prep
PMP Exam Prep Boot Camp
PMP Renewal Program
PMP Exam Prep Question of the Week Series
- PMP Question of the Week: Perform Quality Assurance
- PMP Question of the Week: Quantitative Data
- PMP Question of the Week: Situational Continuum Leadership
- PMP Question of the Week: Stakeholder Register
- PMP Question of the Week: Plan Risk Responses
- PMP Question of the Week: Performance Improvement
- PMP Question of the Week: Budgets
- PMP Question of the Week: EAC
- PMP Question of the Week: Quality Control Techniques
- PMP Question of the Week: Outlining Project Roles
- PMP Question of the Week: Engage Stakeholders
- PMP Question of the Week: Breakdown Structures
- PMP Question of the Week: Quality Management
- PMP Question of the Week: Decision Tree
- PMP Question of the Week: CV
- PMP Question of the Week: Critical Path
- PMP Question of the Week: Project Cost Management
- PMP Question of the Week: Change Request
- PMP Question of the Week: Contract Complete
- PMP Question of the Week: Control Procurements
- PMP Question of the Week: Control Risks
- PMP Question of the Week: Change Requests
- PMP Question of the Week: Plan Communications Management
- PMP Question of the Week: Stakeholder Concerns
- PMP Question of the Week: Effective Communication
- PMP Question of the Week: Project Review
- PMP Question of the Week: Task Duration Predecessor
- PMP Question of the Week: Risk Impacts
- PMP Question of the Week: Change Order Request Next Steps
- PMP Question of the Week: Project Initiator
- PMP Question of the Week: Project Charter
- PMP Question of the Week: Documented Scope Changes
- PMP Question of the Week: Legal Issues
- PMP Question of the Week: Estimate at Completion
- PMP Question of the Week: Statement of Work
- PMP Question of the Week: Risk Strategies
- PMP Question of the Week: Qualitative Risk Analysis
- PMP Question of the Week: Estimate Duration
- PMP Question of the Week: Traceability Matrix
- PMP Question of the Week: Specialized Tool
- PMP Question of the Week: EAC Calculation
- PMP Question of the Week: Prospective Sellers
- PMP Question of the Week: Enterprise Environmental Factor
- PMP Question of the Week: Define Scope Process
Please support our Sponsors here :