PMP Formula of the Week: S-Curve
An S-curve for your project’s PV, EV and AC show AC above PV and EV below PV. What does this indicate?
Read moreAn S-curve for your project’s PV, EV and AC show AC above PV and EV below PV. What does this indicate?
Read moreAs the seller, you are completing a project under a fixed-price incentive fee contract, with a fixed price of $130,000. The incentive (or penalty) is set at $2,000 per week for each week that the project is under (or over) schedule. When you deliver the project two weeks late, how much money will you receive?
Read moreWhat formula is used to determine To-Complete Performance Index (TCPI)?
Read moreWhat is the CPI if PV = $10,000, EV = $9,000 and AC = $9,000?
Read moreWhat condition does a Schedule Performance Index (SPI) of 1 mean for a project?